| 11-Oct-02 | Numbers are Approximate Only-- Not for Quotation or Duplication | |||||||||
| Corel Centre Case Study-- Crashing the Schedule | ||||||||||
| By using both a Project Manager/Construction Manager and a GC with a GMP, the Development/Architectural team | ||||||||||
| was able to bring the GC on the same side of the table. Benefits included faster construction at higher levels of quality. | ||||||||||
| TCs bid competitively and cost savings* were shared by the Developer, the GC and the PM. | ||||||||||
| The contingency allowance was used to ensure quality and to cope with Cos. | ||||||||||
| Cost savings came from three sources-- 1. faster construction, 2. competively bid subs, 3. innovations in the field**. | ||||||||||
| Another factor came into play as well: by completing the project earlier, revenues (and greater revenues) flowed to the | ||||||||||
| Ottawa Senators and the Building Owners sooner, especially as compared to the much smaller, city-owned Civic Centre. | ||||||||||
| Also by completing the building sooner, interim financing costs are reduced. | ||||||||||
| To guage these effects of faster constrution, see below. | ||||||||||
| Constrcution Cost | CAD | |||||||||
| Land | 100 | acres | $150,000 | $15,000,000 | ||||||
| Architecture/Engineering | $8,500,000 | |||||||||
| Legal | $3,000,000 | |||||||||
| Infrastructure | $40,000,000 | |||||||||
| Financing Fees | $8,000,000 | |||||||||
| F,F&E | $9,000,000 | |||||||||
| Building, Landscaping, Parking | 550,000 | s.f | $275 | $151,250,000 | ||||||
| Contingencies | $7,500,000 | |||||||||
| Total | $242,250,000 | |||||||||
| By shaving 8 months off the construction schedule (from 30 months to 22), the Corel Centre enjoyed reduced | ||||||||||
| interim financing costs and higher reveneues | ||||||||||
| Financing Costs Savings | ||||||||||
| Savings | 8 | 12 | 10% | $16,150,000 | ||||||
| Revenues | ||||||||||
| Civic Centre | $35,000,000 | |||||||||
| Corel Centre | $65,000,000 | |||||||||
| Increased Revenues | $20,000,000.00 | |||||||||
| Total Savings and Increased Revenues from Crashing the Schedule | $36,150,000.00 | |||||||||
| * note: the reverse also applies. GCs and PMs may be penalized if projects are late. | ||||||||||
| ** e.g., splitting the building into four quadrants each with their own construction manager and tower crane. | ||||||||||