11-Oct-02 Numbers are Approximate Only-- Not for Quotation or Duplication
Corel Centre Case Study-- Crashing the Schedule
By using both a Project Manager/Construction Manager and a GC with a GMP, the Development/Architectural team
was able to bring the GC on the same side of the table. Benefits included faster construction at higher levels of quality.
TCs bid competitively and cost savings* were shared by the Developer, the GC and the PM.
The contingency allowance was used to ensure quality and to cope with Cos.
Cost savings came  from three sources-- 1. faster construction, 2. competively bid subs, 3. innovations in the field**.
Another factor came into play as well: by completing the project earlier, revenues (and greater revenues) flowed to the
Ottawa Senators and the Building Owners sooner, especially as compared to the much smaller, city-owned Civic Centre.
Also by completing the building sooner, interim financing costs are reduced.
To guage these effects of faster constrution, see below.
Constrcution Cost CAD
Land 100 acres $150,000 $15,000,000
Architecture/Engineering $8,500,000
Legal $3,000,000
Infrastructure $40,000,000
Financing Fees $8,000,000
F,F&E $9,000,000
Building, Landscaping, Parking 550,000 s.f $275 $151,250,000
Contingencies $7,500,000
Total $242,250,000
By shaving 8 months off the construction schedule (from 30 months to 22), the Corel Centre enjoyed reduced
interim financing costs and higher reveneues
Financing Costs Savings
Savings 8 12 10% $16,150,000
Revenues
Civic Centre $35,000,000
Corel Centre $65,000,000
Increased Revenues  $20,000,000.00
Total Savings and Increased Revenues from Crashing the Schedule  $36,150,000.00
* note: the reverse also applies. GCs and PMs may be penalized if projects are late.
** e.g., splitting the building into four quadrants each with their own construction manager and tower crane.