Kosmic2001


Project Start Date: Thu 9/13/01
Project Finish Date: Fri 11/16/01

Task_Data

IDTask_NameDurationStart_DateFinish_DatePredecessorsResource_Names
1start1 dayThu 9/13/01Thu 9/13/01  
2decide date1 dayThu 9/13/01Thu 9/13/01  
3budget and proposal for event1 dayFri 9/14/01Fri 9/14/011,2 
4finance committee38 daysMon 9/17/01Wed 11/7/011,2 
5class approval0 daysFri 9/14/01Fri 9/14/013 
6CSAAS1 dayMon 9/17/01Mon 9/17/013 
7faculty board approval1 dayWed 9/19/01Wed 9/19/013 
8press release # 10 daysWed 9/19/01Wed 9/19/017 
9set up kosmic committees1 dayFri 9/14/01Fri 9/14/012 
10materials Acq. Committee35 daysFri 9/14/01Thu 11/1/012 
11room and installations design committee10 daysMon 9/17/01Fri 9/28/019 
12music, performance & acts committee15 daysMon 9/17/01Fri 10/5/019 
13tickets, logo & t-shirt committee10 daysMon 9/17/01Fri 9/28/019 
14poster & adv. Committee10 daysMon 9/17/01Fri 9/28/019 
15PR Committee3 daysFri 9/14/01Tue 9/18/012 
16F&B concessions committee5 daysMon 9/17/01Fri 9/21/019 
17Construction Committee29 daysMon 9/17/01Thu 10/25/019 
18documentation committee1 dayMon 9/17/01Mon 9/17/019 
19web committee5 daysMon 9/17/01Fri 9/21/019 
20safety during constr. Comm.3 daysMon 9/17/01Wed 9/19/019 
21safety during event comm.1 dayMon 9/17/01Mon 9/17/019 
22sponsorships committee10 daysMon 9/17/01Fri 9/28/019 
23sign up acts 4 daysMon 10/8/01Thu 10/11/0112 
24sign up DJs4 daysMon 10/8/01Thu 10/11/0112 
25sign up performance artists4 daysMon 10/8/01Thu 10/11/0112 
26press release # 20 daysThu 10/11/01Thu 10/11/0123,24,25 
27theme unveiling1 dayTue 10/16/01Tue 10/16/0126 
28ticket production10 daysMon 10/1/01Fri 10/12/0113 
29posters up1 dayWed 10/17/01Wed 10/17/0114,27 
30ticket sales13 daysWed 10/17/01Fri 11/2/0128,27 
31t-shirt sales13 daysWed 10/17/01Fri 11/2/0127,28 
32construction starts5 daysFri 10/26/01Thu 11/1/0117 
33VIP Room construction4 daysFri 11/2/01Wed 11/7/0132 
34lighting set up1 dayThu 11/1/01Thu 11/1/01  
35DJ Calls # 11 dayMon 10/29/01Mon 10/29/01  
36sound set up1 dayThu 11/1/01Thu 11/1/01  
37sponsors signs up1 dayWed 10/31/01Wed 10/31/01  
38F&B Conc. Set up1 dayWed 10/31/01Wed 10/31/01  
39DJ calls # 21 dayFri 11/2/01Fri 11/2/01  
40fire retardent spraying5 daysThu 10/25/01Wed 10/31/01  
41final cleanup1 dayThu 11/1/01Thu 11/1/0140 
42construction ends1 dayThu 11/1/01Thu 11/1/0140 
43fire marshal insp.1 dayFri 11/2/01Sat 11/3/0142 
44hydro inspection1 dayFri 11/2/01Fri 11/2/0141 
45sound check0 daysSat 11/3/01Sat 11/3/0143 
46F&B Inventory0 daysSat 11/3/01Sat 11/3/0143 
47Cash Management0 daysSat 11/3/01Sat 11/3/0143 
48event safety0 daysSat 11/3/01Sat 11/3/0143 
49event happens0 daysSat 11/3/01Sat 11/3/0143 
50return equipment5 daysMon 11/5/01Fri 11/9/0149 
51tear down3 daysMon 11/5/01Wed 11/7/0149 
52cash settlement5 daysMon 11/5/01Fri 11/9/0149 
53clean up3 daysMon 11/5/01Wed 11/7/0149 
54thank you to sponsors3 daysMon 11/5/01Wed 11/7/0149 
55brief next year's kosmic org.10 daysMon 11/5/01Fri 11/16/0149