| Sample Certificate for Payment | 04-Jan-02 | |||||||
| To: Acme Development | ||||||||
| Project: MNOP Building | ||||||||
| This is to certify that in accordance with the contract dated _________________, the Contractor __________________ | ||||||||
| has completed work to the value of $____________________ not including GST or other taxes as of the date _________________ | ||||||||
| The Contractor is entitled to payment of $__________________________ plus GST of $______________ | ||||||||
| for work performed and holdback release due for the period _______________________. | ||||||||
| Statement of Account | ||||||||
| Original Contract Price | $3,200,000.00 | a | ||||||
| Authorized Change Orders to Date | $ 110,000.00 | b | ||||||
| Current Contract Price | $3,310,000.00 | c = a + b | ||||||
| Total Certified Construction to Date | $1,778,000.00 | d | ||||||
| Holdback | 10% | $ 177,800.00 | e = d * 10% | |||||
| Holdback Released to Date | $ 52,000.00 | f | ||||||
| Current Holdback | $ 125,800.00 | g = e - f | ||||||
| Total Certified Construction less Current Holdback | $1,652,200.00 | h = d - g | ||||||
| Total Certified Construction less Current Holdback from last Certificate | $1,027,825.00 | i | ||||||
| Amount of Current Contract Price Payable under this Certificate | $ 624,375.00 | j = h - i | ||||||
| GST Payable | 7% | $ 43,706.25 | k = j * 7% | |||||
| Amount Payable under this Certificate | $ 668,081.25 | l = j + k | ||||||
| Balance of Contract unpaid after payment under this Certificate | $1,033,425.00 | m = c - h - j | ||||||