| ID | Task Name | Duration | Start | Finish | Resource Names | % Complete |
| 1 | Start | 0 days | Mon 10/16/06 | Mon 10/16/06 | | 0% |
| 2 | Apply for Bldg. Permit | 14 days | Mon 10/16/06 | Thu 11/2/06 | Leo | 0% |
| 3 | Apply for Hyrdo Permit | 14 days | Mon 10/16/06 | Thu 11/2/06 | Bert | 0% |
| 4 | Apply for Gas Permit | 10 days | Mon 10/16/06 | Fri 10/27/06 | Len | 0% |
| 5 | Site Work | 16 days | Fri 11/3/06 | Fri 11/24/06 | | 0% |
| 6 | Install Culvert and Gravel Driveway | 2 days | Fri 11/3/06 | Mon 11/6/06 | Earth | 0% |
| 7 | Septic Tank and Septic Field | 7 days | Fri 11/3/06 | Mon 11/13/06 | Earth | 0% |
| 8 | Well | 3 days | Fri 11/3/06 | Tue 11/7/06 | Developer | 0% |
| 9 | Foundation and Footing Excavation | 3 days | Fri 11/3/06 | Tue 11/7/06 | Earth | 0% |
| 10 | Rough-in Plumbing | 2 days | Wed 11/8/06 | Thu 11/9/06 | Gergon | 0% |
| 11 | Pour Footings | 3 days | Fri 11/10/06 | Tue 11/14/06 | Dalma | 0% |
| 12 | Pour Foundation Walls | 5 days | Wed 11/15/06 | Tue 11/21/06 | Dalma | 0% |
| 13 | Tar/Waterproof Foundation | 2 days | Wed 11/22/06 | Thu 11/23/06 | Dalma | 0% |
| 14 | Pour Floor Slab | 3 days | Wed 11/22/06 | Fri 11/24/06 | Dalma | 0% |
| 15 | Tile drainage around foundation | 2 days | Wed 11/22/06 | Thu 11/23/06 | Dalma | 0% |
| 16 | Conduct Foundation Inspection | 1 day | Fri 11/24/06 | Fri 11/24/06 | City | 0% |
| 17 | Backfill | 2 days | Wed 11/22/06 | Thu 11/23/06 | Earth | 0% |
| 18 | Steel Delivery | 1 day | Fri 11/24/06 | Fri 11/24/06 | Pemco | 0% |
| 19 | Dumpster Delivery | 1 day | Fri 11/24/06 | Fri 11/24/06 | Rutkowski | 0% |
| 20 | Lumber and Truss Delivery | 1 day | Fri 11/24/06 | Fri 11/24/06 | Kott | 0% |
| 21 | Windows and Doors (Interior and Exterior) Selection | 5 days | Fri 11/3/06 | Thu 11/9/06 | Dawn | 0% |
| 22 | Siding Selection | 5 days | Fri 11/3/06 | Thu 11/9/06 | Dawn | 0% |
| 23 | Roof Shingles Selection | 5 days | Fri 11/3/06 | Thu 11/9/06 | Dawn | 0% |
| 24 | Carpet, Ceramic, Wood, Plastic Laminate Flooring Selection | 5 days | Fri 11/3/06 | Thu 11/9/06 | Dawn | 0% |
| 25 | Winter Heating Salamanders (if required) | 1 day | Fri 11/24/06 | Fri 11/24/06 | Home Depot | 0% |
| 26 | Framing | 23 days | Mon 11/27/06 | Wed 12/27/06 | | 0% |
| 27 | Lay 1st Floor Sleepers, Sub-floor | 2 days | Mon 11/27/06 | Tue 11/28/06 | Laforce | 0% |
| 28 | Frame 1st Floor Walls | 5 days | Wed 11/29/06 | Tue 12/5/06 | Laforce | 0% |
| 29 | Install 2nd Floor Joists | 2 days | Wed 12/6/06 | Thu 12/7/06 | Laforce | 0% |
| 30 | Frame 2nd Floor Decking | 2 days | Fri 12/8/06 | Mon 12/11/06 | Laforce | 0% |
| 31 | Frame 2nd Floor Walls | 5 days | Tue 12/12/06 | Mon 12/18/06 | Laforce | 0% |
| 32 | Crane | 1 day | Tue 12/19/06 | Tue 12/19/06 | TBD | 0% |
| 33 | Erect Steel | 1 day | Wed 12/20/06 | Wed 12/20/06 | TBD | 0% |
| 34 | Lift Trusses | 1 day | Thu 12/21/06 | Thu 12/21/06 | TBD | 0% |
| 35 | Frame Roof | 3 days | Fri 12/22/06 | Tue 12/26/06 | Laforce | 0% |
| 36 | Conduct Framing Inspection | 1 day | Wed 12/27/06 | Wed 12/27/06 | City | 0% |
| 37 | Shingles Delivery | 1 day | Tue 12/19/06 | Tue 12/19/06 | Nepean Building | 0% |
| 38 | Sheathing (House Wrap) | 16 days | Wed 12/20/06 | Wed 1/10/07 | | 0% |
| 39 | Install 1st Floor Sheathing | 2 days | Wed 12/20/06 | Thu 12/21/06 | Laforce | 0% |
| 40 | Install 2nd Floor Sheathing | 2 days | Thu 12/28/06 | Fri 12/29/06 | Laforce | 0% |
| 41 | Install Roof Sheathing | 3 days | Thu 12/28/06 | Mon 1/1/07 | Laforce | 0% |
| 42 | Install Asphalt Shingle Roofing System | 7 days | Tue 1/2/07 | Wed 1/10/07 | Laforce or Timmons | 0% |
| 43 | Windows and Doors | 3 days | Thu 12/28/06 | Mon 1/1/07 | | 0% |
| 44 | Hang Exterior Doors | 3 days | Thu 12/28/06 | Mon 1/1/07 | Laforce | 0% |
| 45 | Install Windows | 3 days | Thu 12/28/06 | Mon 1/1/07 | Laforce | 0% |
| 46 | Exterior Finishes and Rough-in | 22 days | Mon 1/1/07 | Tue 1/30/07 | | 0% |
| 47 | Install Wall System (Siding) | 8 days | Mon 1/1/07 | Wed 1/10/07 | McCormick | 0% |
| 48 | Select and Purchase Plumbing and Lighting Fixtures and Appliances | 20 days | Mon 1/1/07 | Fri 1/26/07 | Dawn | 0% |
| 49 | Select and Purchase Cabinets and Counters | 20 days | Mon 1/1/07 | Fri 1/26/07 | Dawn | 0% |
| 50 | Eavestroughing | 2 days | Mon 1/29/07 | Tue 1/30/07 | McCormick | 0% |
| 51 | Rough-in plumbing | 3 days | Mon 1/1/07 | Wed 1/3/07 | Gergon | 0% |
| 52 | Conduct Rough-in Plumbing Inspection | 1 day | Thu 1/4/07 | Thu 1/4/07 | City | 0% |
| 53 | Rough-in Heating/AC Duct Work | 4 days | Mon 1/1/07 | Thu 1/4/07 | Len | 0% |
| 54 | Rough-in Electrical | 3 days | Mon 1/1/07 | Wed 1/3/07 | Lorne | 0% |
| 55 | Conduct Rough-in Electrical Inspection | 1 day | Thu 1/4/07 | Thu 1/4/07 | City | 0% |
| 56 | Install Mechanical, Heating and AC Systems | 7 days | Thu 1/11/07 | Fri 1/19/07 | Len | 0% |
| 57 | Install Gas Fireplace | 1 day | Mon 1/22/07 | Mon 1/22/07 | Len | 0% |
| 58 | Rough-in Communications | 2 days | Mon 1/1/07 | Tue 1/2/07 | Lorne | 0% |
| 59 | Interior Finishes | 54 days | Thu 1/4/07 | Tue 3/20/07 | | 0% |
| 60 | Hang Interior Doors | 3 days | Thu 1/11/07 | Mon 1/15/07 | Laforce | 0% |
| 61 | Plumbing Fixtures | 4 days | Fri 1/5/07 | Wed 1/10/07 | Gergon | 0% |
| 62 | Conduct Finish Plumbing Inspection | 1 day | Thu 1/11/07 | Thu 1/11/07 | City | 0% |
| 63 | Insulation and Vapour Barrier | 6 days | Fri 1/12/07 | Fri 1/19/07 | Bert | 0% |
| 64 | Conduct Insulation Inspection | 1 day | Mon 1/22/07 | Mon 1/22/07 | City | 0% |
| 65 | Install Drywall, Taping and Sanding | 6 days | Tue 1/23/07 | Tue 1/30/07 | Lang | 0% |
| 66 | Install Lighting Fixtures | 2 days | Thu 1/4/07 | Fri 1/5/07 | Pat | 0% |
| 67 | Install Millwork and Trim | 5 days | Wed 1/31/07 | Tue 2/6/07 | Pat | 0% |
| 68 | Painting | 8 days | Wed 2/7/07 | Fri 2/16/07 | Bert | 0% |
| 69 | Install Flooring | 10 days | Mon 2/19/07 | Fri 3/2/07 | Pat | 0% |
| 70 | Install Cabinets and Counters | 5 days | Mon 3/5/07 | Fri 3/9/07 | Pat | 0% |
| 71 | Install Appliances | 2 days | Mon 3/12/07 | Tue 3/13/07 | Pat | 0% |
| 72 | Landscaping and Grounds Work | 4 days | Wed 3/14/07 | Mon 3/19/07 | Bert | 0% |
| 73 | Final Grading Gravel Driveway | 1 day | Wed 3/14/07 | Wed 3/14/07 | Earth | 0% |
| 74 | Cleanup for occupancy | 2 days | Thu 3/15/07 | Fri 3/16/07 | Bert | 0% |
| 75 | Perform final walk-through inspection | 1 day | Mon 3/19/07 | Mon 3/19/07 | Bert | 0% |
| 76 | Complete final inspection for certificate of occupancy | 1 day | Tue 3/20/07 | Tue 3/20/07 | City | 0% |