CPM





Project Start:
Project Finish:
Thu 4/1/04
Tue 3/20/07


Tasks


ID
Task Name
DurationStartFinishResource Names% Complete
1
Start
0 daysMon 10/16/06Mon 10/16/06 0%
2
Apply for Bldg. Permit
14 daysMon 10/16/06Thu 11/2/06Leo0%
3
Apply for Hyrdo Permit
14 daysMon 10/16/06Thu 11/2/06Bert0%
4
Apply for Gas Permit
10 daysMon 10/16/06Fri 10/27/06Len0%
5
Site Work
16 daysFri 11/3/06Fri 11/24/06 0%
6
Install Culvert and Gravel Driveway
2 daysFri 11/3/06Mon 11/6/06Earth0%
7
Septic Tank and Septic Field
7 daysFri 11/3/06Mon 11/13/06Earth0%
8
Well
3 daysFri 11/3/06Tue 11/7/06Developer0%
9
Foundation and Footing Excavation
3 daysFri 11/3/06Tue 11/7/06Earth0%
10
Rough-in Plumbing
2 daysWed 11/8/06Thu 11/9/06Gergon0%
11
Pour Footings
3 daysFri 11/10/06Tue 11/14/06Dalma0%
12
Pour Foundation Walls
5 daysWed 11/15/06Tue 11/21/06Dalma0%
13
Tar/Waterproof Foundation
2 daysWed 11/22/06Thu 11/23/06Dalma0%
14
Pour Floor Slab
3 daysWed 11/22/06Fri 11/24/06Dalma0%
15
Tile drainage around foundation
2 daysWed 11/22/06Thu 11/23/06Dalma0%
16
Conduct Foundation Inspection
1 dayFri 11/24/06Fri 11/24/06City0%
17
Backfill
2 daysWed 11/22/06Thu 11/23/06Earth0%
18
Steel Delivery
1 dayFri 11/24/06Fri 11/24/06Pemco0%
19
Dumpster Delivery
1 dayFri 11/24/06Fri 11/24/06Rutkowski0%
20
Lumber and Truss Delivery
1 dayFri 11/24/06Fri 11/24/06Kott0%
21
Windows and Doors (Interior and Exterior) Selection
5 daysFri 11/3/06Thu 11/9/06Dawn0%
22
Siding Selection
5 daysFri 11/3/06Thu 11/9/06Dawn0%
23
Roof Shingles Selection
5 daysFri 11/3/06Thu 11/9/06Dawn0%
24
Carpet, Ceramic, Wood, Plastic Laminate Flooring Selection
5 daysFri 11/3/06Thu 11/9/06Dawn0%
25
Winter Heating Salamanders (if required)
1 dayFri 11/24/06Fri 11/24/06Home Depot0%
26
Framing
23 daysMon 11/27/06Wed 12/27/06 0%
27
Lay 1st Floor Sleepers, Sub-floor
2 daysMon 11/27/06Tue 11/28/06Laforce0%
28
Frame 1st Floor Walls
5 daysWed 11/29/06Tue 12/5/06Laforce0%
29
Install 2nd Floor Joists
2 daysWed 12/6/06Thu 12/7/06Laforce0%
30
Frame 2nd Floor Decking
2 daysFri 12/8/06Mon 12/11/06Laforce0%
31
Frame 2nd Floor Walls
5 daysTue 12/12/06Mon 12/18/06Laforce0%
32
Crane
1 dayTue 12/19/06Tue 12/19/06TBD0%
33
Erect Steel
1 dayWed 12/20/06Wed 12/20/06TBD0%
34
Lift Trusses
1 dayThu 12/21/06Thu 12/21/06TBD0%
35
Frame Roof
3 daysFri 12/22/06Tue 12/26/06Laforce0%
36
Conduct Framing Inspection
1 dayWed 12/27/06Wed 12/27/06City0%
37
Shingles Delivery
1 dayTue 12/19/06Tue 12/19/06Nepean Building0%
38
Sheathing (House Wrap)
16 daysWed 12/20/06Wed 1/10/07 0%
39
Install 1st Floor Sheathing
2 daysWed 12/20/06Thu 12/21/06Laforce0%
40
Install 2nd Floor Sheathing
2 daysThu 12/28/06Fri 12/29/06Laforce0%
41
Install Roof Sheathing
3 daysThu 12/28/06Mon 1/1/07Laforce0%
42
Install Asphalt Shingle Roofing System
7 daysTue 1/2/07Wed 1/10/07Laforce or Timmons0%
43
Windows and Doors
3 daysThu 12/28/06Mon 1/1/07 0%
44
Hang Exterior Doors
3 daysThu 12/28/06Mon 1/1/07Laforce0%
45
Install Windows
3 daysThu 12/28/06Mon 1/1/07Laforce0%
46
Exterior Finishes and Rough-in
22 daysMon 1/1/07Tue 1/30/07 0%
47
Install Wall System (Siding)
8 daysMon 1/1/07Wed 1/10/07McCormick0%
48
Select and Purchase Plumbing and Lighting Fixtures and Appliances
20 daysMon 1/1/07Fri 1/26/07Dawn0%
49
Select and Purchase Cabinets and Counters
20 daysMon 1/1/07Fri 1/26/07Dawn0%
50
Eavestroughing
2 daysMon 1/29/07Tue 1/30/07McCormick0%
51
Rough-in plumbing
3 daysMon 1/1/07Wed 1/3/07Gergon0%
52
Conduct Rough-in Plumbing Inspection
1 dayThu 1/4/07Thu 1/4/07City0%
53
Rough-in Heating/AC Duct Work
4 daysMon 1/1/07Thu 1/4/07Len0%
54
Rough-in Electrical
3 daysMon 1/1/07Wed 1/3/07Lorne0%
55
Conduct Rough-in Electrical Inspection
1 dayThu 1/4/07Thu 1/4/07City0%
56
Install Mechanical, Heating and AC Systems
7 daysThu 1/11/07Fri 1/19/07Len0%
57
Install Gas Fireplace
1 dayMon 1/22/07Mon 1/22/07Len0%
58
Rough-in Communications
2 daysMon 1/1/07Tue 1/2/07Lorne0%
59
Interior Finishes
54 daysThu 1/4/07Tue 3/20/07 0%
60
Hang Interior Doors
3 daysThu 1/11/07Mon 1/15/07Laforce0%
61
Plumbing Fixtures
4 daysFri 1/5/07Wed 1/10/07Gergon0%
62
Conduct Finish Plumbing Inspection
1 dayThu 1/11/07Thu 1/11/07City0%
63
Insulation and Vapour Barrier
6 daysFri 1/12/07Fri 1/19/07Bert0%
64
Conduct Insulation Inspection
1 dayMon 1/22/07Mon 1/22/07City0%
65
Install Drywall, Taping and Sanding
6 daysTue 1/23/07Tue 1/30/07Lang0%
66
Install Lighting Fixtures
2 daysThu 1/4/07Fri 1/5/07Pat0%
67
Install Millwork and Trim
5 daysWed 1/31/07Tue 2/6/07Pat0%
68
Painting
8 daysWed 2/7/07Fri 2/16/07Bert0%
69
Install Flooring
10 daysMon 2/19/07Fri 3/2/07Pat0%
70
Install Cabinets and Counters
5 daysMon 3/5/07Fri 3/9/07Pat0%
71
Install Appliances
2 daysMon 3/12/07Tue 3/13/07Pat0%
72
Landscaping and Grounds Work
4 daysWed 3/14/07Mon 3/19/07Bert0%
73
Final Grading Gravel Driveway
1 dayWed 3/14/07Wed 3/14/07Earth0%
74
Cleanup for occupancy
2 daysThu 3/15/07Fri 3/16/07Bert0%
75
Perform final walk-through inspection
1 dayMon 3/19/07Mon 3/19/07Bert0%
76
Complete final inspection for certificate of occupancy
1 dayTue 3/20/07Tue 3/20/07City0%

Resources


IDNameGroupMax UnitsPeak Units
1Leo 100%100%
2Bert 100%200%
3Len 100%100%
4Earth 100%300%
5Developer 100%100%
6Gergon 100%100%
7Dalma 100%300%
8City 100%200%
9Pemco 100%100%
10Rutkowski 100%100%
11Kott 100%100%
12Home Depot 100%100%
13Laforce 100%400%
14TBD 100%100%
15Laforce or Timmons 100%100%
16Dawn 100%400%
17McCormick 100%100%
18Lorne 100%200%
19Lang 100%100%
20Pat 100%100%
21Nepean Building 100%100%

Assignments


Task IDTask NameResource NameWorkStartFinish% Work Complete
2Apply for Bldg. PermitLeo112 hrsMon 10/16/06Thu 11/2/060%
3Apply for Hyrdo PermitBert112 hrsMon 10/16/06Thu 11/2/060%
4Apply for Gas PermitLen80 hrsMon 10/16/06Fri 10/27/060%
6Install Culvert and Gravel DrivewayEarth16 hrsFri 11/3/06Mon 11/6/060%
7Septic Tank and Septic FieldEarth56 hrsFri 11/3/06Mon 11/13/060%
8Well Developer24 hrsFri 11/3/06Tue 11/7/060%
9Foundation and Footing ExcavationEarth24 hrsFri 11/3/06Tue 11/7/060%
10Rough-in PlumbingGergon16 hrsWed 11/8/06Thu 11/9/060%
11Pour FootingsDalma24 hrsFri 11/10/06Tue 11/14/060%
12Pour Foundation WallsDalma40 hrsWed 11/15/06Tue 11/21/060%
13Tar/Waterproof FoundationDalma16 hrsWed 11/22/06Thu 11/23/060%
14Pour Floor SlabDalma24 hrsWed 11/22/06Fri 11/24/060%
15Tile drainage around foundationDalma16 hrsWed 11/22/06Thu 11/23/060%
16Conduct Foundation InspectionCity8 hrsFri 11/24/06Fri 11/24/060%
17BackfillEarth16 hrsWed 11/22/06Thu 11/23/060%
18Steel DeliveryPemco8 hrsFri 11/24/06Fri 11/24/060%
19Dumpster DeliveryRutkowski8 hrsFri 11/24/06Fri 11/24/060%
20Lumber and Truss DeliveryKott8 hrsFri 11/24/06Fri 11/24/060%
21Windows and Doors (Interior and Exterior) SelectionDawn40 hrsFri 11/3/06Thu 11/9/060%
22Siding SelectionDawn40 hrsFri 11/3/06Thu 11/9/060%
23Roof Shingles SelectionDawn40 hrsFri 11/3/06Thu 11/9/060%
24Carpet, Ceramic, Wood, Plastic Laminate Flooring SelectionDawn40 hrsFri 11/3/06Thu 11/9/060%
25Winter Heating Salamanders (if required)Home Depot8 hrsFri 11/24/06Fri 11/24/060%
27Lay 1st Floor Sleepers, Sub-floorLaforce16 hrsMon 11/27/06Tue 11/28/060%
28Frame 1st Floor WallsLaforce40 hrsWed 11/29/06Tue 12/5/060%
29Install 2nd Floor JoistsLaforce16 hrsWed 12/6/06Thu 12/7/060%
30Frame 2nd Floor DeckingLaforce16 hrsFri 12/8/06Mon 12/11/060%
31Frame 2nd Floor WallsLaforce40 hrsTue 12/12/06Mon 12/18/060%
32CraneTBD8 hrsTue 12/19/06Tue 12/19/060%
33Erect SteelTBD8 hrsWed 12/20/06Wed 12/20/060%
34Lift TrussesTBD8 hrsThu 12/21/06Thu 12/21/060%
35Frame RoofLaforce24 hrsFri 12/22/06Tue 12/26/060%
36Conduct Framing InspectionCity8 hrsWed 12/27/06Wed 12/27/060%
37Shingles DeliveryNepean Building8 hrsTue 12/19/06Tue 12/19/060%
39Install 1st Floor SheathingLaforce16 hrsWed 12/20/06Thu 12/21/060%
40Install 2nd Floor SheathingLaforce16 hrsThu 12/28/06Fri 12/29/060%
41Install Roof SheathingLaforce24 hrsThu 12/28/06Mon 1/1/070%
42Install Asphalt Shingle Roofing SystemLaforce or Timmons56 hrsTue 1/2/07Wed 1/10/070%
44Hang Exterior DoorsLaforce24 hrsThu 12/28/06Mon 1/1/070%
45Install WindowsLaforce24 hrsThu 12/28/06Mon 1/1/070%
47Install Wall System (Siding)McCormick64 hrsMon 1/1/07Wed 1/10/070%
48Select and Purchase Plumbing and Lighting Fixtures and AppliancesDawn160 hrsMon 1/1/07Fri 1/26/070%
49Select and Purchase Cabinets and CountersDawn160 hrsMon 1/1/07Fri 1/26/070%
50EavestroughingMcCormick16 hrsMon 1/29/07Tue 1/30/070%
51Rough-in plumbingGergon24 hrsMon 1/1/07Wed 1/3/070%
52Conduct Rough-in Plumbing InspectionCity8 hrsThu 1/4/07Thu 1/4/070%
53Rough-in Heating/AC Duct WorkLen32 hrsMon 1/1/07Thu 1/4/070%
54Rough-in ElectricalLorne24 hrsMon 1/1/07Wed 1/3/070%
55Conduct Rough-in Electrical InspectionCity8 hrsThu 1/4/07Thu 1/4/070%
56Install Mechanical, Heating and AC SystemsLen56 hrsThu 1/11/07Fri 1/19/070%
57Install Gas FireplaceLen8 hrsMon 1/22/07Mon 1/22/070%
58Rough-in CommunicationsLorne16 hrsMon 1/1/07Tue 1/2/070%
60Hang Interior DoorsLaforce24 hrsThu 1/11/07Mon 1/15/070%
61Plumbing FixturesGergon32 hrsFri 1/5/07Wed 1/10/070%
62Conduct Finish Plumbing InspectionCity8 hrsThu 1/11/07Thu 1/11/070%
63Insulation and Vapour BarrierBert48 hrsFri 1/12/07Fri 1/19/070%
64Conduct Insulation InspectionCity8 hrsMon 1/22/07Mon 1/22/070%
65Install Drywall, Taping and SandingLang48 hrsTue 1/23/07Tue 1/30/070%
66Install Lighting FixturesPat16 hrsThu 1/4/07Fri 1/5/070%
67Install Millwork and TrimPat40 hrsWed 1/31/07Tue 2/6/070%
68PaintingBert64 hrsWed 2/7/07Fri 2/16/070%
69Install FlooringPat80 hrsMon 2/19/07Fri 3/2/070%
70Install Cabinets and CountersPat40 hrsMon 3/5/07Fri 3/9/070%
71Install AppliancesPat16 hrsMon 3/12/07Tue 3/13/070%
72Landscaping and Grounds WorkBert32 hrsWed 3/14/07Mon 3/19/070%
73Final Grading Gravel DrivewayEarth8 hrsWed 3/14/07Wed 3/14/070%
74Cleanup for occupancyBert16 hrsThu 3/15/07Fri 3/16/070%
75Perform final walk-through inspectionBert8 hrsMon 3/19/07Mon 3/19/070%
76Complete final inspection for certificate of occupancyCity8 hrsTue 3/20/07Tue 3/20/070%