Project Start Date: Tue 1/15/02
Project Finish Date: Tue 7/30/02
| ID |
Task_Name |
Duration | Start_Date | Finish_Date | Predecessors | Resource_Names |
|---|---|---|---|---|---|---|
| 1 |
start |
0 days | Tue 1/15/02 | Tue 1/15/02 | ||
| 2 |
survey and zoning |
1 wk | Tue 1/15/02 | Mon 1/21/02 | ||
| 3 |
architectural drawings |
4 wks | Tue 1/22/02 | Mon 2/18/02 | 2 | |
| 4 |
pick fixtures |
2 wks | Tue 2/19/02 | Mon 3/4/02 | 3 | |
| 5 |
working drawings |
2 wks | Tue 2/19/02 | Mon 3/4/02 | 3 | |
| 6 |
select GC |
3 wks | Tue 3/5/02 | Mon 3/25/02 | 4 | |
| 7 |
prepare permits |
1 wk | Tue 2/26/02 | Mon 3/4/02 | 5FS-5 days | |
| 8 |
obtain permits |
4 wks | Tue 3/5/02 | Mon 4/1/02 | 7 | |
| 9 |
build flat |
80.44 days | Tue 4/2/02 | Tue 7/23/02 | 8,6 | |
| 10 |
site prep. |
5 days | Tue 4/2/02 | Mon 4/8/02 | 8 | |
| 11 |
foundation work |
5 days | Tue 4/9/02 | Mon 4/15/02 | 10 | |
| 12 |
lay floor |
6 days | Tue 4/16/02 | Fri 6/28/02 | 11 | |
| 13 |
frame walls |
1.14 days | Mon 7/1/02 | Tue 7/2/02 | 12 | framers[700%] |
| 14 |
construct roof |
0.8 days | Tue 7/2/02 | Tue 7/2/02 | 13 | framers[500%] |
| 15 |
enclose building |
0.17 wks | Tue 7/2/02 | Wed 7/3/02 | 13,14 | framers[600%] |
| 16 |
electrical fit up |
1 wk | Tue 7/2/02 | Tue 7/9/02 | 13,4 | eletrician |
| 17 |
plumbing fit up |
1 wk | Tue 7/2/02 | Tue 7/9/02 | 13,4 | plumber |
| 18 |
inspections |
4 days | Wed 7/3/02 | Tue 7/9/02 | 15 | |
| 19 |
drywall |
0.33 wks | Tue 7/9/02 | Thu 7/11/02 | 13,18 | drywallers[300%] |
| 20 |
trim and mill work |
1 wk | Thu 7/11/02 | Thu 7/18/02 | 19,16,4,15 | cabinet maker |
| 21 |
paint interior |
8 days | Thu 7/11/02 | Tue 7/23/02 | 19 | painters |
| 22 |
occupancy permit |
3 days | Tue 7/9/02 | Fri 7/12/02 | 18 | |
| 23 |
move-in |
1 wk | Tue 7/23/02 | Tue 7/30/02 | 22,21 | |
| 24 |
finish |
0 days | Tue 7/30/02 | Tue 7/30/02 | 23 |