testproject


Project Start Date: Tue 1/15/02
Project Finish Date: Tue 7/30/02

Task_Data

ID
Task_Name
Duration Start_Date Finish_Date Predecessors Resource_Names
1
start
0 days Tue 1/15/02 Tue 1/15/02    
2
survey and zoning
1 wk Tue 1/15/02 Mon 1/21/02    
3
architectural drawings
4 wks Tue 1/22/02 Mon 2/18/02 2  
4
pick fixtures
2 wks Tue 2/19/02 Mon 3/4/02 3  
5
working drawings
2 wks Tue 2/19/02 Mon 3/4/02 3  
6
select GC
3 wks Tue 3/5/02 Mon 3/25/02 4  
7
prepare permits
1 wk Tue 2/26/02 Mon 3/4/02 5FS-5 days  
8
obtain permits
4 wks Tue 3/5/02 Mon 4/1/02 7  
9
build flat
80.44 days Tue 4/2/02 Tue 7/23/02 8,6  
10
site prep.
5 days Tue 4/2/02 Mon 4/8/02 8  
11
foundation work
5 days Tue 4/9/02 Mon 4/15/02 10  
12
lay floor
6 days Tue 4/16/02 Fri 6/28/02 11  
13
frame walls
1.14 days Mon 7/1/02 Tue 7/2/02 12 framers[700%]
14
construct roof
0.8 days Tue 7/2/02 Tue 7/2/02 13 framers[500%]
15
enclose building
0.17 wks Tue 7/2/02 Wed 7/3/02 13,14 framers[600%]
16
electrical fit up
1 wk Tue 7/2/02 Tue 7/9/02 13,4 eletrician
17
plumbing fit up
1 wk Tue 7/2/02 Tue 7/9/02 13,4 plumber
18
inspections
4 days Wed 7/3/02 Tue 7/9/02 15  
19
drywall
0.33 wks Tue 7/9/02 Thu 7/11/02 13,18 drywallers[300%]
20
trim and mill work
1 wk Thu 7/11/02 Thu 7/18/02 19,16,4,15 cabinet maker
21
paint interior
8 days Thu 7/11/02 Tue 7/23/02 19 painters
22
occupancy permit
3 days Tue 7/9/02 Fri 7/12/02 18  
23
move-in
1 wk Tue 7/23/02 Tue 7/30/02 22,21  
24
finish
0 days Tue 7/30/02 Tue 7/30/02 23