| Sample Certificate for Payment | (revised - BGL) | 07-Jan-02 | |||||
| To: Acme Development | |||||||
| Project: MNOP Building | |||||||
| This is to certify that in accordance with the contract dated _________________, the Contractor __________________ | |||||||
| has completed work to the value of $____________________ not including GST or other taxes as of the date _______________ | |||||||
| The Contractor is entitled to payment of $__________________________ plus GST of $______________ | |||||||
| for work performed less cumulative holdbacks _______________________. | |||||||
| Statement of Account | |||||||
| Original Contract Price | $ 3,200,000.00 | a | known | ||||
| Authorized Change Orders to Date | $ 110,000.00 | b | known | ||||
| Current Total Contract Price | $ 3,310,000.00 | c | a+b | ||||
| Total Certified Construction Completion to Date | $ 1,778,000.00 | d | determined | ||||
| Holdback | 10% | $ 177,800.00 | e | 10% of d | |||
| Total Certified Construction less Current Holdback | $ 1,600,200.00 | f | d-e | ||||
| Previous approved payment certificate #__________ | $ 1,153,625.00 | g | known | ||||
| ( Cumulative Total - incl. all holdbacks) | |||||||
| Current Contract Amount Payable under this Certificate | $ 446,575.00 | h | f-g | ||||
| GST Payable | 7% | $ 31,260.25 | I | 7%of h | |||
| Amount Payable under this Certificate | $ 477,835.25 | j | h+I | ||||
| Balance of Contract unpaid after payment under this Certificate | $ 1,263,225.00 | k | c-f-h | ||||
| NOTE: | |||||||
| Holdback is cumulative throughout contract and applies to all completed works to be held pending completion of | |||||||
| contract in full. | |||||||
| Previous example showed roll over of holdback releaesable with each payment after prescrbed period | |||||||
| but which leaves the owner with effective holdback of only the current amount payable from time to time and at the | |||||||
| end of the project holding only 10% of final payment. | |||||||